First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• preparations for the installation of the playground are underway.
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• work on finishing the public usage places (95% complete) is underway, finishing the hall, facade work on the 1st floor (80% complete), installation of radiators and meters (30% complete), landscaping (planting plants, installing irrigation and outdoor lighting systems), arranging a fountain, installing public usage places fixtures, and installing a pump room;
• installation of boilers has begun.
Fifth phase (1-B, Kryshtaleva Street)
• roofing has been completed and window installation is almost complete (except for floors 2-3);
• electrical works, installation of water supply and heating systems (70% complete), facade and plastering works (30% complete), installation of gas supply and fire safety systems, screed arrangement (10% complete) are in progress;
• preparatory work for the dismantling of the crane has begun;
• in the last part of the underground parking lot, the pouring of vertical elements (walls and pylons) has been completed; preparatory work has begun for the pouring of the parking lot floor slab.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025