Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", June 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• preparations for the installation of the playground are underway.

Third phase (1-A, Kryshtaleva Street)

• house is commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• work on finishing the public usage places (95% complete) is underway, finishing the hall, facade work on the 1st floor (80% complete), installation of radiators and meters (30% complete), landscaping (planting plants, installing irrigation and outdoor lighting systems), arranging a fountain, installing public usage places fixtures, and installing a pump room;

• installation of boilers has begun.

Fifth phase (1-B, Kryshtaleva Street)

• roofing has been completed and window installation is almost complete (except for floors 2-3);

• electrical works, installation of water supply and heating systems (70% complete), facade and plastering works (30% complete), installation of gas supply and fire safety systems, screed arrangement (10% complete) are in progress;

• preparatory work for the dismantling of the crane has begun;

• in the last part of the underground parking lot, the pouring of vertical elements (walls and pylons) has been completed; preparatory work has begun for the pouring of the parking lot floor slab.