First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• work on the enter to the second part of the underground parking lot has begun.
Second phase (11-A, Oksamytova Street)
• plastering works are completed;
• screed is being made on 16-17 floors, communications - on the 17th floor;
• facade works are underway.
Third phase (1-A, Kryshtaleva Street)
• radiators are being installed;
• connection to networks (gas, electricity) continues;
• finishing works have started on the ground floor (in the lobby);
• work on entrance groups continues;
• installation of boilers is completed.
Fourth phase (1, Kryshtaleva Street)
• plumbing work continues (installation of risers);
• installation of windows has started.
Fifth phase (1-B, Kryshtaleva Street)
• the foundation slab is made;
• tower crane installation is completed;
• work on vertical walls has begun.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.