First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• work on the enter to the second part of the underground parking lot has begun.
Second phase (11-A, Oksamytova Street)
• plastering works are completed;
• screed is being made on 16-17 floors, communications - on the 17th floor;
• facade works are underway.
Third phase (1-A, Kryshtaleva Street)
• radiators are being installed;
• connection to networks (gas, electricity) continues;
• finishing works have started on the ground floor (in the lobby);
• work on entrance groups continues;
• installation of boilers is completed.
Fourth phase (1, Kryshtaleva Street)
• plumbing work continues (installation of risers);
• installation of windows has started.
Fifth phase (1-B, Kryshtaleva Street)
• the foundation slab is made;
• tower crane installation is completed;
• work on vertical walls has begun.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026