Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", March 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• waterproofing works in the second part of the underground parking lot are being performed.

Second phase (11-A, Oksamytova Street)

• roofing works are in progress.

Third phase (1-A, Kryshtaleva Street)

• finishing works in common areas are continuing.

Fourth phase (1, Kryshtaleva Street)

• monolithic-frame work continues on the 17th floor;

• completed brickwork of the walls on the 12th floor;

• plumbing work have started.

Fifth phase (1-B, Kryshtaleva Street)

• work on borehole injection piles has been completed.