First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the adjacent territory around the house is partially completed.
Second phase (11-A, Oksamytova Street)
• planting of flowers and lawn has been completed, and an irrigation system has been installed;
• preparation for the playground installation is underway.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• arrangement of the adjacent territory around the house is partially completed.
Fourth phase (1, Kryshtaleva Street)
• installation and commissioning of the fire safety system, as well as the installation of railings, have been completed;
• work on finishing the public usage places is underway (95% complete), finishing the hall, facade work on the 1st floor (80% complete), installation of radiators, installation of meters, landscaping (planting plants, installation of irrigation and outdoor lighting systems);
• the fountain arrangement, installation of luminaires in the public usage places, installation of the pump room, and preparations for the boiler installation are underway.
Fifth phase (1-B, Kryshtaleva Street)
• installation of windows (17-18 floors), roofing (90% complete), electrical work, installation of water supply and heating systems (60% complete) are underway;
• facade and plastering works, installation of gas supply and fire safety systems have begun;
• preparation for the screed arrangement is underway;
• the foundation slab in the last part of the underground parking lot has been poured, and the vertical elements (walls and pylons) are being poured.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025