Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", May 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• planting of flowers and lawn has been completed, and an irrigation system has been installed;

• preparation for the playground installation is underway.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation and commissioning of the fire safety system, as well as the installation of railings, have been completed;

• work on finishing the public usage places is underway (95% complete), finishing the hall, facade work on the 1st floor (80% complete), installation of radiators, installation of meters, landscaping (planting plants, installation of irrigation and outdoor lighting systems);

• the fountain arrangement, installation of luminaires in the public usage places, installation of the pump room, and preparations for the boiler installation are underway.

Fifth phase (1-B, Kryshtaleva Street)

• installation of windows (17-18 floors), roofing (90% complete), electrical work, installation of water supply and heating systems (60% complete) are underway;

• facade and plastering works, installation of gas supply and fire safety systems have begun;

• preparation for the screed arrangement is underway;

• the foundation slab in the last part of the underground parking lot has been poured, and the vertical elements (walls and pylons) are being poured.