Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", July 2022

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the local area around the house is partially completed;

• work continues on the arrangement of lighting and ventilation systems in the second part of the underground parking.

Second phase (11-A, Oksamytova Street)

• interior finishing on the floors (works on two floors is completed);

• facade arrangement of the basement floor (300 sq. m. is ready);

• installation of radiators (installed on two floors);

• installation of tiles on cold transitions (50% done);

• work on the improvement of the adjacent territory around the house continues;

• completed work on arrangement of lightning protection on the roof.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• partially completed arrangement of the adjacent territory around the house.

Fourth phase (1, Kryshtaleva Street)

• craftsmen are working on the installation of a ventilated facade;

• arrangement of internal gas supply is in progress.

Fifth phase (1-B, Kryshtaleva Street)

• brickwork continues (on the 6th floor).