First phase (9-A, Oksamytova Street)
• house is commissioned;
• all apartments are sold and occupied;
• arrangement of the local area around the house is partially completed;
• work continues on the arrangement of lighting and ventilation systems in the second part of the underground parking.
Second phase (11-A, Oksamytova Street)
• interior finishing on the floors (works on two floors is completed);
• facade arrangement of the basement floor (300 sq. m. is ready);
• installation of radiators (installed on two floors);
• installation of tiles on cold transitions (50% done);
• work on the improvement of the adjacent territory around the house continues;
• completed work on arrangement of lightning protection on the roof.
Third phase (1-A, Kryshtaleva Street)
• house in commissioned;
• partially completed arrangement of the adjacent territory around the house.
Fourth phase (1, Kryshtaleva Street)
• craftsmen are working on the installation of a ventilated facade;
• arrangement of internal gas supply is in progress.
Fifth phase (1-B, Kryshtaleva Street)
• brickwork continues (on the 6th floor).
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026