Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", October 2020

First stage (9-A, Oksamitova Street)

• the house is put into operation;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• works on monolithic frame are being carried out in the second part of the underground parking lot.

Second stage (11-A, Oksamytova Street)

• brick masonry is nearing completion;

• windows are installed on 10-13 floors;

• plastering of walls and slopes (9th floor) continues.

Third stage (1-A, Kryshtaleva Street)

• plumbing and floor screed is completed;

• facade works are underway (12-14 floors);

• finishing works are underway (5-6 floors).

Fourth stage (1, Kryshtaleva Street)

• monolithic frame works are underway at the 11th floor level.