First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• work on arrangement of fire-prevention systems and electric installation works proceed; the installation of hinged metal structures at the entrance to the parking lot has been completed.
Second phase (11-A, Oksamytova Street)
• arrangement of public usage places (facade works on the first floor, tile laying and arrangement of stairwells) continues.
Third phase (1-A, Kryshtaleva Street)
• the house is commissioned;
• the arrangement of the adjacent territory around the house has been partially completed.
Fourth phase (1, Kryshtaleva Street)
• plastering works, installation of heating and works on a floor cap have been almost completed.
Fifth phase (1-B, Kryshtaleva Street)
• monolithic frame works on the 12th floor are underway;
• brickwork proceeds (on the 3rd floor).
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (AUGUST 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.08.2025
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: AUGUST 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.08.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: AUGUST 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
21.08.2025