Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", December 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• work on arrangement of fire-prevention systems and electric installation works proceed; the installation of hinged metal structures at the entrance to the parking lot has been completed.

Second phase (11-A, Oksamytova Street)

• arrangement of public usage places (facade works on the first floor, tile laying and arrangement of stairwells) continues.

Third phase (1-A, Kryshtaleva Street)

• the house is commissioned;

• the arrangement of the adjacent territory around the house has been partially completed.

Fourth phase (1, Kryshtaleva Street)

• plastering works, installation of heating and works on a floor cap have been almost completed.

Fifth phase (1-B, Kryshtaleva Street)

• monolithic frame works on the 12th floor are underway;

• brickwork proceeds (on the 3rd floor).