Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
90%
5
stage
60%

Progress in construction RC "Crystal Avenue", May 2020

First stage (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and partially occupied;

• the arrangement of the adjacent territory around the house has been partially completed.

Second stage (11-A, Oksamytova Street)

• completed monolithic frame works at the level of the 10th floor;

• finished brickwork of external walls up to the 9th floor;

• completion of monolithic stairs installation at the level of the 9th floor;

• completed installation of aerated concrete inter-apartment walls with a mineral wool layer;

• monolithic frame works are being carried out at the level of the 11th floor.

Third stage (1-A, Kryshtaleva Street)

• the technical floor is blocked;

• all monolithic works have been completed;

• brickwork from a red ceramic block has reached the 15th floor;

• monolithic stairs construction is completed;

• installation of windows has started.

Fourth stage (1, Kryshtaleva Street)

• the floor slab of the building has been made;

• completed installation of vertical basement structures