First phase (9-A, Oksamytova Street)
• the house is commissioned;
• all apartments are sold and occupied;
• the arrangement of the adjacent territory around the house has been partially completed;
• works on arrangement of fire-fighting systems and electrical installation works in the second part of the underground parking continue.
Second phase (11-A, Oksamytova Street)
• start-up and adjustment works take place in elevators;
• the membrane is being installed on the roof;
• installation of cold transition fences is completed;
• installation of balconies on the upper floors has begun.
Third phase (1-A, Kryshtaleva Street)
• installation of a playground continues;
Fourth phase (1, Kryshtaleva Street)
• plastering works are almost finished (1, 15, 16 floors remain) and roof insulation is coming to an end;
• installation of heating continues (on 11-13 floors);
• work on the floor cap (8-9 floors) continues.
Fifth phase (1-B, Kryshtaleva Street)
• works on monolithic frame on the 8th floor are underway.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025