Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", October 2021

First phase (9-A, Oksamytova Street)

• the house is commissioned;

• all apartments are sold and occupied;

• the arrangement of the adjacent territory around the house has been partially completed;

• works on arrangement of fire-fighting systems and electrical installation works in the second part of the underground parking continue.

Second phase (11-A, Oksamytova Street)

• start-up and adjustment works take place in elevators;

• the membrane is being installed on the roof;

• installation of cold transition fences is completed;

• installation of balconies on the upper floors has begun.

Third phase (1-A, Kryshtaleva Street)

• installation of a playground continues;

Fourth phase (1, Kryshtaleva Street)

• plastering works are almost finished (1, 15, 16 floors remain) and roof insulation is coming to an end;

• installation of heating continues (on 11-13 floors);

• work on the floor cap (8-9 floors) continues.

Fifth phase (1-B, Kryshtaleva Street)

• works on monolithic frame on the 8th floor are underway.