The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of house commissioning and connecting the gas supply is ongoing.
The fifth stage (1-B Kryshtaleva str.)
• facade works (90% complete), interior finishing and electrical works (40% complete), finishing of the public usage places and staircases (15% complete), installation of elevators (70% complete), installation of apartment doors (80% complete), installation of technical doors (50% complete), installation of window and door structures (1-2 floors) are underway;
• the last part of the underground parking lot is undergoing waterproofing (50% complete).