The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of house commissioning and connecting the gas supply is ongoing.
The fifth stage (1-B Kryshtaleva str.)
• facade works (90% complete), interior finishing and electrical works (40% complete), finishing of the public usage places and staircases (15% complete), installation of elevators (70% complete), installation of apartment doors (80% complete), installation of technical doors (50% complete), installation of window and door structures (1-2 floors) are underway;
• the last part of the underground parking lot is undergoing waterproofing (50% complete).
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: FEBRUARY 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
28.02.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (FEBRUARY 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
28.02.2026
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: FEBRUARY 2026
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”.
24.02.2026