Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
75%

Progress in construction RC "Crystal Avenue", October 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

Second phase (11-A, Oksamytova Street)

• house is commissioned;

Third phase (1-A, Kryshtaleva Street)

• house is commissioned;

Fourth phase (1, Kryshtaleva Street)

• installation of a playground, a fountain and an access control system for the building has been completed;

• work on laying lawns and planting trees has begun;

• preparations for laying the rubber coating and preparing the building for commissioning are underway.

Fifth phase (1-B, Kryshtaleva Street)

• facade works are in progress (80% complete), plastering works (90% complete), screed installation (70% complete), gas supply installation (60% complete), and fire door installation;

• preparations for interior finishing and electrical works have begun.

• in the last part of the underground parking lot, the parking lot floor slab has been completed; preparations for insulation and waterproofing of the parking lot are underway.