First phase (9-A, Oksamytova Street)
• house is commissioned;
Second phase (11-A, Oksamytova Street)
• house is commissioned;
Third phase (1-A, Kryshtaleva Street)
• house is commissioned;
Fourth phase (1, Kryshtaleva Street)
• installation of a playground, a fountain and an access control system for the building has been completed;
• work on laying lawns and planting trees has begun;
• preparations for laying the rubber coating and preparing the building for commissioning are underway.
Fifth phase (1-B, Kryshtaleva Street)
• facade works are in progress (80% complete), plastering works (90% complete), screed installation (70% complete), gas supply installation (60% complete), and fire door installation;
• preparations for interior finishing and electrical works have begun.
• in the last part of the underground parking lot, the parking lot floor slab has been completed; preparations for insulation and waterproofing of the parking lot are underway.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025