Progress in construction RC "Crystal Avenue", February 2024

First phase (9-A, Oksamytova Street)

• house is commissioned;

• all apartments are sold and occupied;

• arrangement of the adjacent territory around the house is partially completed.

Second phase (11-A, Oksamytova Street)

• small architectural forms (trash bins, benches) have been installed;

• preparation for installation of the children's playground is underway.

Third phase (1-A, Kryshtaleva Street)

• house in commissioned;

• arrangement of the adjacent territory around the house is partially completed.

Fourth phase (1, Kryshtaleva Street)

• installation of equipment in the control room and doors on the 1st floor is completed;

• work on finishing the public usage places is ongoing (55% complete), commissioning of elevator equipment, facade work on the 1st floor (60% complete).

Fifth phase (1-B, Kryshtaleva Street)

• brickwork of the walls is completed;

• installation of windows is in progress.