Progress in construction RC "Crystal Avenue", November 2025

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  all construction and documentation work has been completed.

The fifth stage (1-B Kryshtaleva str.)

•  finishing works in the lobby, installation of irrigation system, testing of all building systems, connection of the building to water and electricity supply networks have been completed.

•  work on the facade of the 1st floor (99% complete), landscaping, and planting of plants is ongoing.

•  the process of commissioning the building and preparing to transfer apartments to investors has begun.

•  landscaping, flooring, and fire safety system installation work is continuing in the last section of the underground parking garage.