The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• all construction and documentation work has been completed.
The fifth stage (1-B Kryshtaleva str.)
• finishing works in the lobby, installation of irrigation system, testing of all building systems, connection of the building to water and electricity supply networks have been completed.
• work on the facade of the 1st floor (99% complete), landscaping, and planting of plants is ongoing.
• the process of commissioning the building and preparing to transfer apartments to investors has begun.
• landscaping, flooring, and fire safety system installation work is continuing in the last section of the underground parking garage.
PHASE 5 OF THE “CRYSTAL AVENUE” RESIDENTIAL COMPLEX HAS BEEN COMMISSIONED
Happy homeowners have already started moving into their cozy apartments.
16.04.2026
PARKING SPACES IN THE “LYPYNSKY” RESIDENTIAL COMPLEX ARE GETTING HIGHER IN PRICE. HURRY AND RESERVE YOUR SPOT!
Spaces ranging from 12.5 to 17.2 m² are available.
15.04.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MARCH 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
31.03.2026