
The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of connecting gas and electricity supply on a permanent basis is underway.
The fifth stage (1-B Kryshtaleva str.)
• installation of technical doors, irrigation system, installation of equipment in the electrical control room and equipment in the water supply pump room has been completed;
• facade works (98% complete), finishing of the public usage places and staircases (85% complete), installation of window and door structures on the 1st and 2nd floors (95% complete), internal and electrical works (90% complete), installation of boilers and radiators (50% complete), landscaping works are in progress;
• preparations for planting have begun;
• the last part of the underground parking lot is undergoing landscaping works, preparations for flooring and installation of the fire safety system.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.12.2025