Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
99%
5
stage
90%

Progress in construction RC "Crystal Avenue", May 2025

The first stage (9-A Oksamytova St.)

• the house is commissioned.

The second stage (11-A Oksamytova St.)

• the house is commissioned.

The third stage (1-A Kryshtaleva str.)

• the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

• the process of connecting gas and electricity supply on a permanent basis is underway.

The fifth stage (1-B Kryshtaleva str.)

• installation of technical doors, irrigation system, installation of equipment in the electrical control room and equipment in the water supply pump room has been completed;

• facade works (98% complete), finishing of the public usage places and staircases (85% complete), installation of window and door structures on the 1st and 2nd floors (95% complete), internal and electrical works (90% complete), installation of boilers and radiators (50% complete), landscaping works are in progress;

• preparations for planting have begun;

• the last part of the underground parking lot is undergoing landscaping works, preparations for flooring and installation of the fire safety system.