
The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• the process of connecting gas and electricity supply on a permanent basis is underway.
The fifth stage (1-B Kryshtaleva str.)
• installation of technical doors, irrigation system, installation of equipment in the electrical control room and equipment in the water supply pump room has been completed;
• facade works (98% complete), finishing of the public usage places and staircases (85% complete), installation of window and door structures on the 1st and 2nd floors (95% complete), internal and electrical works (90% complete), installation of boilers and radiators (50% complete), landscaping works are in progress;
• preparations for planting have begun;
• the last part of the underground parking lot is undergoing landscaping works, preparations for flooring and installation of the fire safety system.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: MAY 2026
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.05.2026
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (MAY 2026)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.05.2026
A CONVENIENT SERVICE FOR RESELLING REAL ESTATE FROM “NOVABUDOVA”
We recommend this platform as a convenient tool for those who want to close a deal quickly and transparently.
29.05.2026