Progress in construction

1
stage
100%
2
stage
100%
3
stage
100%
4
stage
100%
5
stage
100%

Progress in construction RC "Crystal Avenue", April 2026

The first stage (9-A Oksamytova St.)

•  the house is commissioned.

The second stage (11-A Oksamytova St.)

•  the house is commissioned.

The third stage (1-A Kryshtaleva str.)

•  the house is commissioned.

Fourth stage (1 Kryshtaleva str.) 

•  the house is commissioned.

The fifth stage (1-B Kryshtaleva str.)

•  the house is commissioned;

•  preparations are underway to begin supplying gas to the building, connect it to DTEK’s power grid, and finalize key contracts;

•  the final stage of landscaping and setting up the stadium area is currently underway.