
The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• connection of electricity supply on a permanent basis and conclusion of major contracts are in progress.
The fifth stage (1-B Kryshtaleva str.)
• outdoor lighting installation completed;
• finishing works in the lobby, installation of the 1st floor facade (90% complete), installation of irrigation, landscaping works, planting of plants, testing of all building systems, connection of the building to water and electricity supply networks, preparation for commissioning of the building, preparation for transfer of housing to investors;
• landscaping, flooring, and fire safety system installation are ongoing in the last section of the underground parking garage.
CONSTRUCTION PROGRESS OF THE “SHCHASLYVYI GRAND” RESIDENTIAL COMPLEX: SEPTEMBER 2025
Herein we are telling you about the construction of the comfort-class residential complex "Shchaslyvyi Grand" in Sofiyivska Borshchahivka.
30.09.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (SEPTEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.
30.09.2025
REPORT ON CONSTRUCTION WORKS IN THE RC “LYPYNSKY”: SEPTEMBER 2025
We invite you to familiarize yourself with the progress of construction works in the business class residential complex “Lypynsky”, located in the street of the same name in Lviv.
26.09.2025