The first stage (9-A Oksamytova St.)
• the house is commissioned.
The second stage (11-A Oksamytova St.)
• the house is commissioned.
The third stage (1-A Kryshtaleva str.)
• the house is commissioned.
Fourth stage (1 Kryshtaleva str.)
• connection of electricity supply on a permanent basis and conclusion of major contracts are in progress.
The fifth stage (1-B Kryshtaleva str.)
• outdoor lighting installation completed;
• finishing works in the lobby, installation of the 1st floor facade (90% complete), installation of irrigation, landscaping works, planting of plants, testing of all building systems, connection of the building to water and electricity supply networks, preparation for commissioning of the building, preparation for transfer of housing to investors;
• landscaping, flooring, and fire safety system installation are ongoing in the last section of the underground parking garage.
WORKING HOURS OF SALES DEPARTMENTS DURING THE HOLIDAYS
From December 31 to January 11 inclusive, the sales and accounting departments will be closed.
30.12.2025
2025 RESULTS FROM “NOVABUDOVA” COMPANY
As a tradition, at the end of the year we summarize our achievements.
30.12.2025
CONSTRUCTION OF THE RESIDENTIAL COMPLEX "CRYSTAL AVENUE": MONTHLY DIGEST (DECEMBER 2025)
Herein we are telling you about the construction progress of the Crystal Avenue residential complex in Petropavlivska Borshchahivka.